Big Boost for Renewables: NHPC Commissions Full 300 MW Karnisar Solar Project in Bikaner, Rajasthan

Karnisar Solar Project Fully Operational, NHPC Set to Power Punjab for 25 Years
Karnisar Solar Project
Indian Masterminds Stories

Bikaner: NHPC Limited, India’s leading hydropower company and a growing force in the renewable energy sector, has successfully commissioned its entire 300 MW Karnisar Solar Project in Bikaner, Rajasthan, marking a significant milestone in India’s clean energy journey.

Final Phase of 85.72 MW Cleared for Operation

The company received the Certificate of Successful Trial Run Completion on October 10, 2025, for the fifth and final phase of the solar project, which included the remaining 85.72 MW capacity. With this certification, the full project is now technically ready for Commercial Operation Date (COD).

Project Ready to Power Punjab for 25 Years

All 300 MW of power generated from this solar installation will be supplied to Punjab State Power Corporation Limited (PSPCL) under a 25-year Power Usage Agreement (PUA).

While the project is fully commissioned, NHPC is currently awaiting:

  • Regulatory approval from the Punjab State Electricity Regulatory Commission (PSERC)
  • Formal consent from PSPCL
  • These are the final formalities before the commencement of commercial operations.

Major Renewable Milestone for NHPC

This commissioning marks a key achievement in NHPC’s diversification into solar and other renewable energy projects, beyond its traditional hydroelectric portfolio.

Read also: NHPC Extends Tenure of Chief Vigilance Officer IFS Santosh Kumar Till June 2026

The Karnisar Solar Project is now set to feed large-scale clean energy into the national grid, strengthening India’s push toward achieving its 500 GW renewable energy target by 2030 and ensuring sustainable energy security for Punjab.

About the Karnisar Solar Project

Location: Bikaner, Rajasthan – a region known for high solar irradiance

Total Capacity: 300 MW

Beneficiary: Punjab State Power Corporation Limited (PSPCL)

Duration of PUA: 25 years

Execution Timeline: Completed in multiple phases, culminating in final phase certification on October 10, 2025

What’s Next?

With all technical milestones achieved, NHPC expects to announce the Commercial Operation Date (COD) shortly, following the anticipated regulatory clearances.

The project is expected to:

  • Offset a significant amount of carbon emissions annually
  • Contribute meaningfully to India’s solar capacity addition
  • Serve as a model for future PSU-led solar ventures

About NHPC

NHPC Limited (formerly National Hydroelectric Power Corporation) is India’s leading hydropower company under the Ministry of Power. Established in 1975, it develops, operates, and maintains hydro, solar, and wind power projects across the country. NHPC is now diversifying into renewable energy, supporting India’s sustainable and clean energy goals.


Indian Masterminds Stories
ADVERTISEMENT
ADVERTISEMENT
Related Stories
ADVERTISEMENT
ADVERTISEMENT
NEWS
nitish
Bihar to Introduce Incentive Policy 2026, Plans to Reopen Closed Sugar Mills and Set Up 25 New Units
yadav
MP CM Mohan Yadav Inaugurates ₹48.71 Crore Nanakheda Stadium Upgrade Ahead of 2030 Commonwealth Games
Ruchi Singh
UPSC CSE 2025: Inspector’s Daughter Ruchi Singh Secures AIR 171, Father Set to Salute Her as IPS Officer
omc
OMC Launches 2 Day Cervical Cancer Vaccination Drive for Women Employees Across Head Office and Mining Units
GAIL PSU
GAIL India Appoints Rohit Mathur as Government Nominee Director to Strengthen Energy Governance
NTPC Green
NTPC Green Energy Commissions 91.6 MW Second Phase of Ayana Kadapa Solar Project, Total Capacity Hits 9,292 MW
grse
GRSE Wins Multiple Awards at 15th ICC PSE Conclave 2026, Cmde P.R. Hari Honoured as ‘CMD of the Year’
Mahanagar Gas Limited MGL
Mahanagar Gas Limited Appoints Deepak Gupta as Chairman to Boost CNG, PNG and Clean Energy Initiatives
ADVERTISEMENT
ADVERTISEMENT
Videos
WhatsApp Image 2026-03-02 at 10.22
Beno Zephine: India’s First 100% Visually Challenged IFS Officer Who Rewrote the Rules of Diplomacy | EXCLUSIVE
Prajesh Kanta Jena
How IFS Prajesh Kanta Jena Empowered Women & Youth at Palamau Tiger Reserve
WhatsApp Image 2026-02-23 at 12.13
Exclusive | From Ridge to River: Prajesh Kanta Jena’s Community-Led Conservation Drive at Palamau
ADVERTISEMENT
UPSC Stories
WEB THUMBNAIL TEMPLATE -3
3 Attempts, 1 Dream: How Indore’s Ananya Sharma Secured AIR 13 in UPSC CSE 2025 After Two Prelims Failures | Exclusive
Ananya Sharma from Indore secured AIR 13 in UPSC CSE 2025 in her third attempt after failing prelims...
WhatsApp Image 2026-03-09 at 2.31
UPSC 2025 Gujarat Topper: Nisar Dishant Amrutlal’s Four-Attempt Journey to AIR 19 | Exclusive
Born in Mumbai with roots in Kutch, Nisar Dishant Amrutlal secured AIR 19 in UPSC CSE 2025 after four...
UPSC CSE 2025: Patna’s Ujjwal Priyank Bags AIR 10 After Missing Final List Earlier | EXCLUSIVE 
UPSC CSE 2025: Patna’s Ujjwal Priyank Bags AIR 10 After Missing Final List Earlier | EXCLUSIVE 
Patna’s Ujjwal Priyank secured AIR 10 in UPSC CSE 2025 after narrowly missing the final list earlier....
Social Media
One-Horned Rhino Calf
Watch: First One-Horned Rhino Calf of 2026 Takes Birth at Jaldapara National Park, IFS Officer Shares Rare Footage
A newborn one-horned rhinoceros calf was spotted at Jaldapara National Park on January 1, 2026. IFS officer...
venomous banded krait
Rare Night Encounter: IFS Officer Spots Highly Venomous Banded Krait During Forest Patrol, Internet Amazed
An IFS officer’s night patrol video of a highly venomous banded krait has gone viral, highlighting India’s...
elephant rescue Karnataka
Heroic Karnataka Elephant Rescue: How a 28-Hour “Impossible Mission” Became a Triumph of Wildlife Care, IFS Parveen Kaswan Shares Video
A trapped elephant was rescued after 28 hours in Karnataka through a massive, expertly coordinated Forest...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Latest
nitish
Bihar to Introduce Incentive Policy 2026, Plans to Reopen Closed Sugar Mills and Set Up 25 New Units
yadav
MP CM Mohan Yadav Inaugurates ₹48.71 Crore Nanakheda Stadium Upgrade Ahead of 2030 Commonwealth Games
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Videos
WhatsApp Image 2026-03-02 at 10.22
Prajesh Kanta Jena
WhatsApp Image 2026-02-23 at 12.13
ADVERTISEMENT
ADVERTISEMENT