Inside the Dhanush Gun Programme Delays and ₹62.10 Crore Loss Over Defective Army Ammunition

Parliament's Public Accounts Committee has flagged a ₹62.10 crore loss linked to defective ammunition supplied to the Indian Army while scrutiny of the Dhanush artillery programme has renewed concerns over production delays, infrastructure and technical skills.
Public Accounts Committee Defence Report
Indian Masterminds Stories

New Delhi: India’s Public Accounts Committee defence report has raised serious concerns over a ₹62.10 crore loss linked to the replacement of defective ammunition supplied to the Indian Army. The parliamentary scrutiny also revisited long delays in the indigenous Dhanush artillery programme and called for stronger quality testing, better planning, skilled manpower and tighter project monitoring. The findings are significant because ammunition reliability and timely artillery modernisation directly affect the Army’s operational preparedness.

The latest parliamentary examination is based on older audit findings of the Comptroller and Auditor General (CAG), but it brings them back into focus with recommendations aimed at preventing similar problems in future defence programmes.

Public Accounts Committee Defence Report: Details of ₹62.10 Crore Defective Ammunition Case

The issue goes back to ammunition supplied by Ordnance Factory Badmal in Odisha to the Indian Army. According to the official CAG findings, the Army reported exudation, or leakage, of explosive material from ammunition that had been supplied in March 2009 and March 2010. Importantly, the ammunition was still within its shelf life when the problem emerged. The problem was linked to the set point, or melting point, of TNT explosive being below the specified range.

Read also: Indian Army’s 2050 Vision Includes AI Humanoid Robots for Counter-Terrorism and Urban Warfare

The CAG found that the TNT set-point value had not been tested at Ordnance Factory Badmal before the explosive mixture was filled into shells. The required testing provision was absent from the Controllerate of Quality Assurance specification.

The factory ultimately had to replace defective ammunition supplied to the Army. The CAG calculated a ₹62.10 crore loss from this replacement.

How Much Ammunition Had to be Replaced

According to the parliamentary committee findings reported after the PAC report was presented, the erstwhile Ordnance Factory Board had to provide 14,159 replacement ammunition rounds free of cost to the Army.

The PAC has now recommended that the Ministry of Defence revisit relevant ammunition-testing specifications and methods, particularly for ammunition under development at ordnance factories.

Why is the Ammunition Problem Important for the Army

A defective artillery round is not only a financial problem. Ammunition must remain safe and reliable during its specified storage life and work correctly when required in training or combat. This is why the PAC has called for stringent quality tests and trials to prevent similar incidents.

The episode also shows how a missing testing requirement can create a chain of problems—from manufacturing and quality assurance to replacement costs and military stock availability.

Public Accounts Committee Defence Report: Dhanush Artillery Delays into Focus

The parliamentary scrutiny is important for another reason: the PAC has also examined the long-running issue of delays in the 155mm/45 calibre Dhanush artillery gun programme. This is not a new concern.

The CAG had already highlighted Dhanush production delays in its Report No. 13 of 2018, and the issue subsequently became a subject for examination by the Public Accounts Committee. Parliamentary committee records show that the PAC continued examining both the Dhanush issue and the ₹62.10 crore ammunition case during 2025-26.

What did the CAG Originally Say About Dhanush

According to the CAG’s official 2018 report, the erstwhile Ordnance Factory Board started development of the electronically upgraded 155mm/45 calibre Dhanush system in 2011. The programme was based on technology obtained during India’s earlier procurement of 155mm/39 calibre guns in 1986.

At the time of the audit, Dhanush had still not fully cleared user trials. The CAG said the delay contributed to the continued shortage of modern artillery guns in the Army.

That historical context matters because Dhanush was intended to help India build a modern artillery capability at home rather than remain heavily dependent on imported systems.

Public Accounts Committee Defence Report: Dhanush Eventually Entered Production

The programme later achieved major milestones. In February 2019, the Ministry of Defence announced bulk production clearance for 114 Dhanush guns. The first six guns were formally handed over to the Indian Army in April that year. The Ministry described Dhanush as India’s first indigenously produced long-range 155mm/45 calibre artillery gun.

The project involved the Ordnance Factory Board and Indian Army, with contributions from organisations including DRDO, DGQA, BEL, SAIL and private-sector companies.

Why did the Dhanush Programme Face Delays

The wider PAC examination has focused on issues including infrastructure, production processes and shortages of specialised technical expertise.

The committee has also highlighted the importance of expertise in areas such as ballistics, gun electronics and integration of advanced sighting systems.

The underlying lesson is that developing a complex weapon domestically requires much more than designing the weapon itself. Manufacturing facilities, skilled engineers, supply chains, testing infrastructure and quality-control systems must all develop together.

The CAG’s earlier finding demonstrates how serious the delay became: although development had begun in 2011, the gun was still awaiting complete user-trial clearance when the 2018 audit examined the programme.

Dhanush is More Than a Replacement Gun

Dhanush represents India’s attempt to use existing artillery knowledge and domestic engineering capability to create a more modern weapon.

Official Ministry of Defence information says the system includes an inertial-navigation-based sighting system, onboard ballistic computation, auto-laying and advanced day-and-night direct firing capability.

Its development therefore represents a wider shift from simply manufacturing an older design toward integrating electronics, navigation and automated fire-control technologies into an Indian artillery platform.

That makes delays especially important: when development takes too long, military requirements and technology can continue changing while a system is still moving through development and production.

What Does PAC Want Changed?

The committee’s examination points toward several broad reforms: stronger quality-control procedures, earlier identification of capability and infrastructure gaps, better technical skills, improved supply-chain management and tighter monitoring of defence projects.

For ammunition specifically, the recommendation is particularly clear—testing specifications and methods should be reviewed so that products under development face stringent quality tests and trials.

For complex indigenous weapons programmes, the larger lesson is to assess manufacturing capacity and technical requirements before large-scale execution begins.

Read also: Indian Army to Procure 450 Carl-Gustaf M4 Launchers: Features, Benefits and and Timeline


Indian Masterminds Stories
Join our WhatsApp Channel
ADVERTISEMENT
ADVERTISEMENT
Related Stories
ADVERTISEMENT
ADVERTISEMENT
NEWS
BPCL Pragati CSR
BPCL’s CSR Initiative Pragati Trains 10,000 Mechanics Across 22 States and 2 Union Territories 
CCPA Fines Dial4Trade ₹10 Lakh Over Ammonium Nitrate
CCPA Fines Dial4Trade ₹10 Lakh Over Ammonium Nitrate Listings
SJVN Rajbhasha Shield
SJVN Wins Rajbhasha Shield Third Prize from Ministry of Power for Hindi Promotion 
fake ias tri[pti
Fake IAS Officer Tripti Singh Rajput Case Widens, ₹50 Lakh+ Fraud Allegations Surface
grse
GRSE Pays ₹147.77 Crore Interim Dividend for FY26; Government Gets ₹110.09 Crore 
BCI Chairman Manan Kumar Mishra
Attorney General Must Be Involved In Key BCI Decisions, Supreme Court Rules
OBC Creamy Layer Case
OBC Creamy Layer Case: Supreme Court To Hear Centre’s Plea On September 17, CSE 2025 Allocation In Focus
Student Protest FIRs
How Article 142 Helped Student Protesters Win Relief From The Supreme Court
ADVERTISEMENT
ADVERTISEMENT
Videos
Keshav kumar
From Police Officer to Forensic Pioneer: How Dr Keshav Kumar Made Science a Weapon Against Crime
ChatGPT Image Aug 20, 2026, 05_46_21 PM
How IPS Officer Keshav Kumar Used Forensics to Crack Gujarat’s Lion Poaching Case
Shakeel Ahmad Ganie IRS Interview
‘My Path Has Not Been Straight’: Shakeel Ahmad Ganie’s Journey to the IRS
ADVERTISEMENT
UPSC Stories
Naveen Kumar Saini UPSC CAPF
After 3 NDA Attempts and a 7-Mark Miss, Naveen Kumar Saini Gets AIR 7 in UPSC CAPF 2025
Naveen Kumar Saini secured AIR 7 in UPSC CAPF 2025 after multiple NDA and SSB failures and missing CAPF...
Pankaj Kamboj
Father Died, Family Turned to Farming: How Pankaj Kamboj Fought His Way to CAPF
After losing his father at 14 and helping his family survive through farming, Pankaj Kamboj turned repeated...
Prachi Jain
A Failed Prelims, A Fractured Leg & One More Shot: How Prachi Jain Made AIR 714
Prachi Jain secured AIR 714 in UPSC CSE 2025 after setbacks, injury and two interviews, and now prepares...
CSR NEWS
BPCL Pragati CSR
BPCL’s CSR Initiative Pragati Trains 10,000 Mechanics Across 22 States and 2 Union Territories 
The programme, implemented with ASDC, equips two-wheeler and four-wheeler mechanics with BS6 technology,...
nbcc
NBCC Wins ‘Champion Emerging’ Award at EXCEED CSR Awards 2026 for Hanle Ambulance Initiative
The Navratna PSU was recognised for procuring an ambulance for Hanle, Leh, strengthening emergency healthcare...
bel
BEL Lays Foundation Stone for Modern Crematorium at Lucknow Cantonment Under CSR Initiative
Rajnath Singh, Yogi Adityanath and BEL CMD Manoj Jain Attend Ceremony; Facility Aims to Provide Dignified...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Latest
BPCL Pragati CSR
BPCL’s CSR Initiative Pragati Trains 10,000 Mechanics Across 22 States and 2 Union Territories 
CCPA Fines Dial4Trade ₹10 Lakh Over Ammonium Nitrate
CCPA Fines Dial4Trade ₹10 Lakh Over Ammonium Nitrate Listings
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Videos
Keshav kumar
ChatGPT Image Aug 20, 2026, 05_46_21 PM
Shakeel Ahmad Ganie IRS Interview
ADVERTISEMENT
ADVERTISEMENT