Lucknow: The Uttar Pradesh government is offering a range of financial and infrastructure incentives to attract large-scale investments in the data centre sector under its new Data Centre Policy 2026. Approved by the state Cabinet on July 6, 2026, the policy aims to add more than 2 GW of data centre capacity and attract investments exceeding ₹2 lakh crore.
The new policy replaces the state’s 2021 Data Centre Policy and focuses on expanding digital infrastructure, encouraging high-capacity data centres and promoting renewable energy adoption.
According to policy documents, the government is targeting Tier III and Tier IV-certified data centres while encouraging new facilities to source at least 50% of their energy requirements from renewable sources by 2030.
Data Centre Investors to Receive Subsidies and Financial Incentives
The policy offers financial assistance to investors establishing data centre parks and individual data centre units.
Read Also: Uttar Pradesh Targets Digital Smart Gram Panchayats Under Rural Development Roadmap for 2047
The major incentives include:
- Interest subsidy: Up to ₹50 crore for data centre parks.
- Capital subsidy: Up to ₹20 crore for individual data centre units.
- Land subsidy: Up to 25% in Madhyanchal and Paschimanchal regions and up to 50% in Bundelkhand and Purvanchal.
- Stamp duty exemption: 100% exemption on land purchased or leased from government authorities.
- Electricity duty exemption: 100% exemption for 10 years.
- Transmission and wheeling charges: Up to 100% exemption, depending on the source of renewable electricity.
- Additional incentives: Special provisions for AI computing infrastructure and green certification.
These incentives are intended to reduce the initial investment and operational costs associated with establishing data centre facilities in the state.
Eligibility Criteria for Data Centre Projects
The policy specifies different capacity and infrastructure requirements for data centre parks, individual units and edge data centres.
The eligibility criteria include:
- Data Centre Park: Minimum 40 MW load
- Data Centre Unit: More than 2 MW but less than 40 MW load
- Edge Data Centre: At least 10 sites, each with 50 kW capacity, and a combined minimum load of 2 MW
The separate eligibility requirements provide a framework for different types and scales of data centre infrastructure.
Policy Targets More Than 2 GW Capacity and ₹2 Lakh Crore Investment
The 2026 policy significantly increases the targets set under the previous framework.
Under the 2021 Data Centre Policy, Uttar Pradesh had targeted 250 MW of capacity and investments worth ₹20,000 crore.
According to state government figures cited in the policy coverage, the sector had recorded the following progress by June 2025:
- Investment: ₹21,342.90 crore.
- Memorandums of Understanding: 29.
- Proposed data centre capacity: 644 MW.
- Operational capacity: 101 MW.
The new policy raises the state’s investment and capacity ambitions, with a target of more than 2 GW in additional data centre capacity.
Greater Noida Data Centre Proposal with AM Green
Another major development in Uttar Pradesh’s data centre investment landscape was the memorandum of understanding signed between the state government and AM Green in January 2026.
The agreement envisaged a 1 GW data centre project in Greater Noida, with a proposed investment of $25 billion.
AI Computing and Renewable Energy Among Policy Priorities
The new policy also places emphasis on infrastructure required for artificial intelligence computing and environmentally sustainable data centre operations.
Additional incentives for AI computing infrastructure are intended to support investments in advanced computing facilities. The policy also provides incentives linked to green certification and renewable electricity sourcing.
With its focus on financial subsidies, land availability, electricity-related exemptions and AI infrastructure, Uttar Pradesh is seeking to expand its position in India’s data centre sector.
The government’s stated targets under the 2026 policy are to attract more than ₹2 lakh crore in investments, add over 2 GW of capacity and encourage renewable energy adoption in newly established data centres.
Read Also: UP: Lucknow Plans 258-Acre AI City with Target of 50 Startups and Thousands of Jobs