Metro Trains to Start Running in MP from Next Year: Chhavi Bhardwaj, MD, MPMRCL

Indian Masterminds Stories

Madhya Pradesh will soon join member states Uttar Pradesh, West Bengal, Rajasthan, Karnataka, and Delhi-NCR in the Metro Rail club. And the IAS officer who is leading the state into joining this club is Ms. Chhavi Bhardwaj. Currently, she is the Managing Director of Madhya Pradesh Metro Rail Corporation Ltd (MPMRCL).

Under her leadership, work on the metro construction project took off at a breakneck speed and is almost nearing completion. Metro trains are now scheduled to start from next year in the state. During an interview to Indian Masterminds, the officer talked about the two metro projects in MP and the challenges she has faced in them. 

EXCERPTS FROM THE INTERVIEW

What are the projects currently going on under Madhya Pradesh Metro Rail Corporation Ltd. (MPMRCL)? 

We have metro plan for two major cities in Madhya Pradesh.  One is in Indore and other one in the state’s capital, Bhopal. Both the projects are currently going on. In Bhopal, we have two corridors covering almost an entire stretch of 30 kms. Similarly, the project going on in Indore covers a 31.5 kms stretch. 

How long will it take for the metro to be up and running in Madhya Pradesh? 

It was important for us to take a time limit and commission the project. However, completing the entire project in both the cities will take time. So, we are focusing on commissioning the first segment, or you can say, the priority corridors. In Bhopal, the corridor runs from AIIMS to Shubash Nagar, covering a 7 km stretch. While in Indore, the corridor is of 17 km, running between Radission Square to Airport with 15 stations in between. We have already recovered the backlog in construction and are hopeful to commence metro trains from September 2023.

Will this project connect the whole city?

Our aim is to ensure better connectivity and respectively cheaper mode of public transport for the people. With the completion of priority corridors in both the cities, people from various parts of the city would be able to come to the commercial centres and premier health institutions. Since Bhopal is more widely spread, so we will have to complete the entire 30 km stretch in order to connect the whole city. Still the 7 km corridor will reach a lot of people. 

Since Bhopal is an old and crowded city, did you face challenges in terms of construction? 

The 7 km corridor which is on priority spreads over the newer part of the city, locally called New Bhopal. This part is comparatively clear, so it was not difficult, as there was very less issues of removal or reinstallation during the construction. In most of the segments, we easily got ROWs (type of easement over the land for transportation) along the median of the road. However, in the centre of Bhopal, we have taken 3 km underground segment, as there was no possibility of cutting through it. 

What about Indore? 

We had to take 7 km underground segment in the heart of Indore. Although the cost of constructing underground metro is thrice the cost of the elevated one, in congested areas where the possibility is zero, we are going ahead with underground metro. Municipal Corporation is there to coordinate and help us. So, we hope to complete the project in time.  


Indian Masterminds Stories
Join our WhatsApp Channel
ADVERTISEMENT
ADVERTISEMENT
Related Stories
ADVERTISEMENT
ADVERTISEMENT
NEWS
UP Police SSS Defence M72 carbines Induction
UP Police Reshuffle: 12 IPS Officers Get New Postings; Abhishek Anjani Singh Assigned to Gorakhpur 
UPSC
UPSC ESE 2027 Exam Schedule Released: Prelims on January 31, Mains on June 18; Check Paper Timings
Navi Mumbai Fake IAS Officer Case
Bihar Promotes 10 IAS Officers: Saran DM Vaibhav Srivastava Among Officials Elevated to Additional Secretary Grade
Ramgarh Road Infrastructure Development
Jharkhand Targets Construction of 12,500 Km of Rural Roads Under Viksit Bharat-G RAM G Scheme
Nalco
NALCO Q2 FY27 Results: Net Profit Rises 28% to Rs 1,835 Crore, H1 Profit Hits Record Rs 3,837 Crore
nmdc resized
NMDC Records 19% Growth in Iron Ore Production in Q2 FY27, H1 Output Rises 23%
MECON-EY-MoU
MECON Signs MoU with Ernst & Young LLP to Promote Investment and Infrastructure Development
Munak Canal Chhath Puja
Delhi CM Rekha Gupta, Nitin Nabin Inaugurate 11-Km Chhath Puja Ghat Along Munak Canal Ahead of Festival 
ADVERTISEMENT
ADVERTISEMENT
Videos
Five years after Kargil, India sent its cricketing heroes to Pakistan where terrorism posed a deadly threat. The man guarding them, former Special Director of Intelligence Bureau, Mr. Yashovardhan Azad, reveals what all went behind the scenes during that crucial tour. 
Trust No One, Said His Instinct in Pakistan
Gajendra Singh Shekhawat
How India Plans to Boost Tourism, Create Jobs and Ease Overcrowding : Gajendra Singh Shekhawat on the Road to 2047
Dr Saket Badola IFS
Beyond Tigers and Safaris: How Corbett Literature Festival Wants to Change the Conservation Conversation
ADVERTISEMENT
UPSC Stories
Aniket Sagar ICoAS
No Coaching, Full-Time Job and Two Attempts: How Aniket Sagar Cleared ICoAS
Aniket Sagar, a chartered accountant from Bundelkhand, cleared UPSC ICoAS 2025 after working at PwC,...
IDAS Himanshu Tembhekar
Should UPSC Aspirants Give Up Their Hobbies? IDAS Officer Himanshu Tembhekar Explains
Should UPSC aspirants give up their hobbies? IDAS officer Himanshu Tembhekar explains how hobbies help...
UPSC Story
He Taught Students to Meet Expenses. Today, Sachin Bhadouria is a Scientist ‘B’ at CWPRS
Sachin Bhadouria overcame financial challenges and a Hindi-medium background to secure AIR 2 in a UPSC...
CSR NEWS
cmpdil
CMPDIL Partners with Tata Steel Foundation to Upgrade Technical Education at ITI Tamar 
The project will modernise training infrastructure with robotic welding technology, digital learning...
NCL CSR Blood Bank Project
NCL Signs ₹1.16 Crore CSR MoU to Establish Blood Bank at District Hospital in Singrauli
The project will fund essential medical equipment, furniture and renovation of the existing building...
REC Foundation Solar Street Light
REC Foundation to Install 350 Solar Street Lights Across Six Districts of West Bengal to Improve Rural Safety 
The CSR initiative, undertaken in partnership with Y4D Foundation, aims to improve night-time safety...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Latest
UP Police SSS Defence M72 carbines Induction
UP Police Reshuffle: 12 IPS Officers Get New Postings; Abhishek Anjani Singh Assigned to Gorakhpur 
UPSC
UPSC ESE 2027 Exam Schedule Released: Prelims on January 31, Mains on June 18; Check Paper Timings
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Videos
Five years after Kargil, India sent its cricketing heroes to Pakistan where terrorism posed a deadly threat. The man guarding them, former Special Director of Intelligence Bureau, Mr. Yashovardhan Azad, reveals what all went behind the scenes during that crucial tour. 
Gajendra Singh Shekhawat
Dr Saket Badola IFS
ADVERTISEMENT
ADVERTISEMENT