New Delhi: DVC CIL Power Private Limited, a 50:50 joint venture between Damodar Valley Corporation (DVC) and Coal India Limited (CIL), has signed a Limited Notice to Proceed (LNTP) with L&T Energy CarbonLite Solutions for the main plant package of the 2×800 MW Chandrapura Thermal Power Station (DC CTPS) in Jharkhand.
The agreement marks an important step towards advancing the 1,600 MW Chandrapura thermal power project, which will use ultra-supercritical technology to improve generation efficiency and reduce specific emissions.
1,600 MW Chandrapura Thermal Power Project
The Chandrapura Thermal Power Station will comprise two ultra-supercritical units, each with a capacity of 800 MW.
Key project details include:
- Project: Chandrapura Thermal Power Station (DC CTPS)
- Location: Jharkhand
- Total capacity: 1,600 MW
- Configuration: 2 × 800 MW
- Technology: Ultra-supercritical
- Project company: DVC CIL Power Private Limited
- JV partners: DVC and Coal India Limited
The project is intended to strengthen power generation capacity and support the growing electricity demand in the region and across the country.
L&T to Execute Main Plant Package
Under the LNTP, L&T Energy CarbonLite Solutions will undertake major activities related to the main plant package.
Its scope will cover:
- Design and engineering
- Manufacturing
- Supply
- Erection
- Testing
- Commissioning
The main equipment covered under the package includes boilers, steam turbines, generators and Electrostatic Precipitators (ESPs).
Ultra-Supercritical Technology to Improve Efficiency
The Chandrapura project will use ultra-supercritical technology, which operates at higher temperature and pressure conditions compared with conventional thermal power technology.
The technology is designed to offer:
- Higher thermal efficiency
- Lower specific emissions
- Improved utilisation of fuel
- More efficient power generation
The adoption of advanced technology is part of the project’s focus on efficient and modern thermal power generation.
Project to Progress After Applicable Conditions
DVC CIL Power Private Limited stated that the project will move to the next stage after fulfilment of the applicable conditions.
These include obtaining the required environmental clearance and completion of the LNTP period.
The signing of the LNTP provides a framework for progressing the main plant package while the stipulated conditions and formalities are completed.
DVC Expanding Power Generation Capacity
DVC said the project represents an important step in its efforts to expand power generation capacity through advanced and efficient technologies.
The 1,600 MW Chandrapura project is expected to contribute to meeting the increasing power demand of the region and the country while supporting the development of modern thermal power infrastructure.
About Damodar Valley Corporation (DVC)
Damodar Valley Corporation (DVC) is a statutory organisation involved in power generation, transmission and distribution, as well as water management in the Damodar Valley region. DVC operates a diversified power generation portfolio and plays an important role in supplying electricity to industries and other consumers in eastern India.
Read also: IRFC Signs ₹4,200 Crore Term Loan Agreement With DVC to Finance Renewable Energy Projects