RVNL Achieves Key Milestones in ₹447.42 Crore Delhi Metro Phase IV Project, Advances 7.3-Km Elevated Corridor

The D2C-02 package covers seven stations on the Pushp Vihar–Lajpat Nagar stretch, with piling, pile caps, precast segments and elevated structures under construction.
Indian Masterminds Stories

New Delhi: Rail Vikas Nigam Limited (RVNL) is making steady progress on its ₹447.42 crore D2C-02 package under Delhi Metro Phase IV, aimed at strengthening public transport connectivity across South Delhi.

The project involves the construction of a 7.298-km elevated viaduct and platform structures for seven metro stations on the Pushp Vihar–Lajpat Nagar stretch. The work forms part of the wider expansion of the Delhi Metro network and is expected to support faster, more sustainable urban mobility in the capital.

RVNL’s Delhi Metro Phase IV Package Covers 7.3-Km Corridor

Under the D2C-02 package, RVNL is responsible for major elevated construction and engineering works along the designated corridor.

The scope of work includes:

  • 863 viaduct piles
  • 208 pile caps
  • More than 2,200 precast segments
  • Six special spans
  • Elevated structures for seven metro stations
  • Construction of a 7.298-km elevated corridor

Piling activities are already underway as construction progresses across multiple fronts.

Read also: RVNL to Roll Out First Vande Bharat Sleeper Prototype from Latur Factory by March 2027 

Key Construction Milestones Achieved

RVNL has reported progress on several important activities under the package.

The company has completed the first working pile, marking an important milestone in the foundation works. In addition, three pile caps have already been constructed.

Other progress includes:

  • Design submissions completed as part of the project execution process
  • Batching plant commissioned
  • Foundation and piling activities progressing
  • Work advancing on elevated corridor structures

These developments indicate that the project has moved forward into active construction and foundation stages.

Pushp Vihar-Lajpat Nagar Corridor to Improve South Delhi Connectivity

The D2C-02 package is expected to strengthen metro connectivity across key areas of South Delhi.

The elevated corridor will provide commuters with an additional public transport option and is expected to offer a faster and more sustainable alternative to road-based travel.

Expansion of metro infrastructure can also support long-term urban mobility and help ease pressure on busy road networks by encouraging greater use of public transportation.

Project Supports Sustainable Urban Mobility

The Delhi Metro Phase IV expansion is part of efforts to strengthen mass rapid transit infrastructure in the National Capital Region.

Improved metro connectivity can provide several benefits, including:

  • Better connectivity between residential and commercial areas
  • Reduced dependence on private vehicles
  • More efficient public transportation
  • Support for sustainable urban development
  • Improved mobility for daily commuters

The RVNL package will contribute to this wider objective through the construction of new elevated infrastructure and metro stations.

RVNL Strengthens Role in Urban Infrastructure

The Delhi Metro Phase IV project further expands RVNL’s involvement in major transportation and urban infrastructure projects.

The company is focusing on engineering-led execution and timely progress across its infrastructure portfolio. Its work on the D2C-02 package highlights its role in supporting large-scale public transport infrastructure and improving connectivity in Indian cities.

About Rail Vikas Nigam Limited (RVNL)

Rail Vikas Nigam Limited (RVNL) is a Navratna Central Public Sector Enterprise under the Ministry of Railways. The company undertakes major rail and transportation infrastructure projects, including new railway lines, bridges, electrification, metro projects and other large-scale infrastructure works across India. RVNL plays an important role in supporting the country’s transportation connectivity and infrastructure development.

Read also: RVNL 23rd AGM: Shareholders Approve ₹0.71 Final Dividend, Review FY26 Financial Performance 


Indian Masterminds Stories
Join our WhatsApp Channel
ADVERTISEMENT
ADVERTISEMENT
Related Stories
ADVERTISEMENT
ADVERTISEMENT
NEWS
Kamlesh Chandra Varshney IRS
Who Is Kamlesh Chandra Varshney? IRS Officer Reappointed as SEBI Whole-Time Member Till 2029
Andhra Pradesh Police
Andhra Pradesh Transfers 9 IPS Officers; Pankaj Meena Named Markapuram SP, Jagadeesh Adahalli Gets Palnadu
Project Saksham
NHAI Unveils New Guidelines for Safer, Access-Controlled High-Speed National Highways
CM Mohan Yadav
MP’s Telecom Manufacturing Plan: Gwalior Zone Takes Centre Stage at Bengaluru Investor Meet
mp tunnel
Madhya Pradesh: Sleemanabad Tunnel Nears Completion, Narmada Water to Reach Rewa Farms
saras mela bihar 2
Bihar Saras Mela 2026: 15 States Join Patna Event Showcasing Rural Women Entrepreneurs
bihar semiconductor
Bihar’s Tech Takeoff: Taiwan, South Korea Eye Semiconductor Opportunities
bihar tourism boost
From Thailand to Bodh Gaya: 28-Member Delegation Explores Bihar’s Buddhist Heritage
ADVERTISEMENT
ADVERTISEMENT
Videos
Keshav kumar
From Police Officer to Forensic Pioneer: How Dr Keshav Kumar Made Science a Weapon Against Crime
ChatGPT Image Aug 20, 2026, 05_46_21 PM
How IPS Officer Keshav Kumar Used Forensics to Crack Gujarat’s Lion Poaching Case
Shakeel Ahmad Ganie IRS Interview
‘My Path Has Not Been Straight’: Shakeel Ahmad Ganie’s Journey to the IRS
ADVERTISEMENT
UPSC Stories
Umar Janj UPSC CAPF AC 2025
After 15 Failures, Umar Janj Finally Heard the Words He Had Been Waiting For: ‘I have made it'
Umar Janj from Jaisalmer secured AIR 160 in UPSC CAPF 2025 after 15+ failures, four attempts, four SSBs...
Abhishek Parmar
NDA Failures, CAPF Setbacks, Then AIR 248:How Abhishek Parmar Overcame Years of Exam Setbacks
Abhishek Parmar became the third generation of his family to enter uniformed service after overcoming...
Naveen Kumar Saini UPSC CAPF
After 3 NDA Attempts and a 7-Mark Miss, Naveen Kumar Saini Gets AIR 7 in UPSC CAPF 2025
Naveen Kumar Saini secured AIR 7 in UPSC CAPF 2025 after multiple NDA and SSB failures and missing CAPF...
CSR NEWS
HURL SHG
HURL Signs MoU to Empower 80–100 SHG Women Through Water Hyacinth Handicraft Training
CSR initiative in Namrup, Assam will provide 80–100 women with advanced skill development, upskilling...
NTPC Kanti CSR
NTPC Kanti Allocates ₹1 Crore CSR Budget to Improve Seven Chhath Ghats in Muzaffarpur
CSR initiative under FY 2026-27 will improve community infrastructure and provide safer, more convenient...
NCL Nanha-Sa-Dil
NCL Launches Second Phase of ‘Nanha-Sa-Dil’ CSR Initiative to Provide Free Cardiac Care to Children
₹9.17 crore programme to organise 700 screening camps, cover 52,500 children and facilitate 500 cardiac...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Latest
Kamlesh Chandra Varshney IRS
Who Is Kamlesh Chandra Varshney? IRS Officer Reappointed as SEBI Whole-Time Member Till 2029
Andhra Pradesh Police
Andhra Pradesh Transfers 9 IPS Officers; Pankaj Meena Named Markapuram SP, Jagadeesh Adahalli Gets Palnadu
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Videos
Keshav kumar
ChatGPT Image Aug 20, 2026, 05_46_21 PM
Shakeel Ahmad Ganie IRS Interview
ADVERTISEMENT
ADVERTISEMENT