Bihar’s ₹845 Crore Munger Four-Lane Nears Completion, Traffic to Start by November 15

The 22.56-km Munger-Mirza Chowki greenfield four-lane has crossed 87% completion and is expected to open by November 15, improving connectivity to Bhagalpur, Banka and Jharkhand.
Indian Masterminds Stories

Patna: Bihar’s Munger-Mirza Chowki Greenfield Four-Lane Project (Package-1) is nearing completion, with 87.14% of the 22.56-km stretch already constructed. Vehicles are expected to start running on the entire route from November 15, 2026.

Built at a cost of around ₹845.27 crore, the road connects Janki Nagar in Munger with Kharia village and is expected to provide faster connectivity towards Bhagalpur, Banka and Jharkhand.

87% Construction Work Completed

According to Road Construction Department Secretary Pankaj Kumar Pal, more than 21 km of the four-lane road has been completed.

The remaining work includes approach roads to the railway overbridge, underpass connectivity and concrete work on a few stretches. The department expects these works to be completed within the scheduled timeline.

Once operational, the road will provide relief from narrow existing routes and traffic congestion in the region.

Read Also: Bihar Saras Mela 2026: 15 States Join Patna Event Showcasing Rural Women Entrepreneurs

Project Faced Flooding and Land Challenges

Construction faced difficulties because the area near the Ganga remains vulnerable to flooding and waterlogging for three to four months every year. This affected the availability of soil required for road embankments.

Land acquisition disputes over compensation also delayed construction on around 9.5 km of the project.

An administrative decision taken on September 22, 2023, helped resolve the land acquisition issues, following which the district administration completed the acquisition in phases.

To overcome the shortage of soil, the department arranged pond ash from NTPC for embankment construction.

Faster Route to Bhagalpur and Jharkhand

The new greenfield road is expected to significantly improve connectivity from Munger towards Bhagalpur, Banka and the Jharkhand border.

It will also strengthen the road connection between Bihar and the Jharkhand side around Mirza Chowki and Sahibganj, supporting inter-state passenger and goods movement.

Better connectivity is expected to reduce travel time and make transportation of agricultural products, minerals and industrial goods easier and more cost-effective.

Easier Access to Healthcare and Education

The project is also expected to benefit residents of Munger, Lakhisarai and nearby rural areas by improving access to major hospitals, medical colleges and educational institutions in Bhagalpur.

The department said the road has been developed using modern construction techniques and safety standards, including underpass facilities, to provide safer and more comfortable travel.

With most of the construction complete, the project is now entering its final phase. If the remaining works finish as scheduled, the new four-lane corridor will open to traffic on November 15, strengthening Bihar’s road network and its connectivity with Jharkhand.

Read Also: Bihar Plans Revival of Closed Sugar Mills, 25 New Units to Boost Industry and Rural Employment


Indian Masterminds Stories
Join our WhatsApp Channel
ADVERTISEMENT
ADVERTISEMENT
Related Stories
ADVERTISEMENT
ADVERTISEMENT
NEWS
bihar 4 lane
Bihar’s ₹845 Crore Munger Four-Lane Nears Completion, Traffic to Start by November 15
karam parv 2026jharkhand
Karam Parv 2026: Hemant Soren Highlights Jharkhand’s Bond With Nature, Culture and Tradition
Suvendu Adhikari
Purulia to Take Off: West Bengal, Centre to Sign UDAN Airport Pact on September 28
cm rekha
Delhi’s New Heritage Push: Govt to Fund 75% of Monument Conservation Projects
GRID-INDIA
GRID-INDIA Holds 17th AGM, Approves Rs 63.32 Lakh Final Dividend, Total Payout Reaches Rs 633.22 Lakh 
SJVN Swachhata Hi Seva 2026
SJVN Conducts Cleanliness Drives, Waste Management Awareness Under Swachhata Hi Seva 2026
Corbett Literature Festival 2026
Corbett Literature Festival 2026 to Debut in Uttarakhand, Bringing Wildlife, Conservation and Literature Together 
CM-Bhagwant-Singh
Punjab CM Mann Opposes FIRs Over Stubble Burning, Backs Cash Incentive for Farmers
ADVERTISEMENT
ADVERTISEMENT
Videos
Keshav kumar
From Police Officer to Forensic Pioneer: How Dr Keshav Kumar Made Science a Weapon Against Crime
ChatGPT Image Aug 20, 2026, 05_46_21 PM
How IPS Officer Keshav Kumar Used Forensics to Crack Gujarat’s Lion Poaching Case
Shakeel Ahmad Ganie IRS Interview
‘My Path Has Not Been Straight’: Shakeel Ahmad Ganie’s Journey to the IRS
ADVERTISEMENT
UPSC Stories
Dr Radhika Mishra MPPSC
“Sports Has Always Been More Than a Career for Me”: Dr Radhika Mishra Clears MPPSC Sports Officer Exam
Dr Radhika Mishra, an Assistant Professor from Gwalior, cleared the MPPSC Sports Officer Examination...
Umar Janj UPSC CAPF AC 2025
After 15 Failures, Umar Janj Finally Heard the Words He Had Been Waiting For: ‘I have made it'
Umar Janj from Jaisalmer secured AIR 160 in UPSC CAPF 2025 after 15+ failures, four attempts, four SSBs...
Abhishek Parmar
NDA Failures, CAPF Setbacks, Then AIR 248:How Abhishek Parmar Overcame Years of Exam Setbacks
Abhishek Parmar became the third generation of his family to enter uniformed service after overcoming...
CSR NEWS
HURL open gyms
HURL Signs MoU With Youth of India Foundation to Install Open Gyms Across Kushinagar
Initiative under “Khelega Bharat, Badhega Bharat” will bring fitness facilities to selected government...
coal-India-limited
Coal India’s CSR Spending Reaches Nearly ₹1,000 Crore Annually, Cumulative Expenditure Touches ₹7,276 Crore
CIL spent ₹7,276 crore against a statutory requirement of ₹5,795 crore from FY 2014-15 to FY 2025-26,...
HURL SHG
HURL Signs MoU to Empower 80–100 SHG Women Through Water Hyacinth Handicraft Training
CSR initiative in Namrup, Assam will provide 80–100 women with advanced skill development, upskilling...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Latest
bihar 4 lane
Bihar’s ₹845 Crore Munger Four-Lane Nears Completion, Traffic to Start by November 15
karam parv 2026jharkhand
Karam Parv 2026: Hemant Soren Highlights Jharkhand’s Bond With Nature, Culture and Tradition
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Videos
Keshav kumar
ChatGPT Image Aug 20, 2026, 05_46_21 PM
Shakeel Ahmad Ganie IRS Interview
ADVERTISEMENT
ADVERTISEMENT