NHPC Secures ₹392.31 Crore Arbitral Award Plus €15.36 Lakh in Subansiri Lower HE Project Case 

Award also includes €15.36 lakh, with the amount eligible for recovery through project tariff under CERC Tariff Regulations, 2024. 
Indian Masterminds Stories

New Delhi: NHPC Limited has disclosed a significant development in a material arbitration matter related to its 2,000 MW Subansiri Lower Hydroelectric Project (HE Project). An Arbitral Tribunal pronounced its award on September 1, 2026, in the arbitration proceedings between M/s BGS-SGS-SOMA and NHPC Limited.

The award includes ₹3,92,31,46,740 (₹392.31 crore) and €15,36,530 (approximately €15.36 lakh). NHPC said the awarded amount is allowable as a project cost under the Central Electricity Regulatory Commission (CERC) Tariff Regulations, 2024, and can therefore be recovered through the project’s tariff.

Arbitral Tribunal Pronounces Award in Subansiri Lower Project Case

The arbitration relates to the work order for the construction of major components of the Subansiri Lower HE Project under Lot SSL-1.

The scope of work covered:

  • Construction of diversion tunnels
  • Construction of coffer dams
  • Construction of the concrete gravity dam
  • Construction of the plunge pool
  • Construction of the cut-off wall

The Arbitral Tribunal pronounced its award on September 1, 2026, resolving the long-standing arbitration matter involving BGS-SGS-SOMA and NHPC.

Read also: NHPC Felicitates Sports Scholars and Medal-Winning Employees on National Sports Day 2026

NHPC Award Amount Against Original Claim

BGS-SGS-SOMA had originally raised a claim of ₹796.87 crore and €28.76 lakh in connection with the work.

The final awarded amount is substantially lower than the original claim.

  • Counterparty: BGS-SGS-SOMA
  • Original Claim: ₹796.87 crore
  • Original Claim: €28.76 lakh
  • Awarded Amount: ₹392.31 crore
  • Awarded Amount: €15.36 lakh
  • Award Date: September 1, 2026
  • Project: Subansiri Lower HE Project (2,000 MW)

The awarded sum includes the principal amount along with interest at 10% per annum, calculated from September 9, 2021, to August 31, 2026.

Award Qualifies as Allowable Project Cost Under CERC Regulations

A key financial implication of the arbitration outcome is that NHPC has stated that the awarded amount qualifies as an allowable project cost under the CERC Tariff Regulations, 2024.

According to the company, this means the amount can be recovered through the project’s tariff.

This regulatory treatment provides NHPC with a mechanism to recover the awarded cost through the tariff framework applicable to the project.

Disclosure Under SEBI Listing Regulations

NHPC disclosed the development to the stock exchanges in compliance with Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.

The disclosure represents a change in the status of the company’s material litigation case under arbitration and follows its earlier communication dated August 14, 2023, concerning material litigation matters under arbitration.

Subansiri Lower Hydroelectric Project

The arbitration matter is linked to the 2,000 MW Subansiri Lower Hydroelectric Project, one of NHPC’s major hydroelectric projects.

The dispute was associated with construction works involving critical components of the project, including diversion tunnels, coffer dams, the concrete gravity dam, plunge pool and cut-off wall.

With the Tribunal’s award dated September 1, 2026, the arbitration matter has reached a significant stage, while the awarded amount will be treated in accordance with the applicable CERC tariff framework.

About NHPC Limited

NHPC Limited is a Navratna Central Public Sector Enterprise under the Ministry of Power, Government of India. The company is India’s leading hydropower development organisation and is also expanding its presence across solar, wind, pumped storage and other renewable energy segments. NHPC is engaged in the development, operation and maintenance of power projects across India.

Read also: NHPC Holds 50th AGM, Proposes ₹0.21 Final Dividend; Targets 50,000 MW Capacity by 2047


Indian Masterminds Stories
Join our WhatsApp Channel
ADVERTISEMENT
ADVERTISEMENT
Related Stories
ADVERTISEMENT
ADVERTISEMENT
NEWS
karnataka high court
Karnataka High Court Strikes Down Enhanced SC/ST Quota, Cites 50% Reservation Limit
Telangana High Court
Judicial Dignity in Focus: Telangana High Court Advocates Stage Protest
bhashini mussorie
India’s AI Push: BHASHINI Brings Voice-First Translation to Global Civil Servants in Mussoorie
india czeck republic defence ties 1
From Joint Ventures to Make in India: Defence Minister Rajnath Singh Strengthens India–Czech Ties
Sanjay Pratap Singh Delhi Metro
Delhi Metro Death Case: Ex-IAS Officer Sanjay Pratap Singh Arrested at Least 3 Times Earlier, Including in 2015 CBI Bribery Case
Raksha Rajya Mantri Sanjay Seth
Building Tomorrow’s Leaders: Raksha Rajya Mantri Sanjay Seth to Chair NCC Conference on Youth Development
Droupadi Murmu National Defence
President Droupadi Murmu Highlights Emerging Security Challenges at 66th National Defence College Meet 
noida development
New Noida Plan: Uttar Pradesh Targets 6 Lakh Jobs Through 20,000-Hectare Expansion
ADVERTISEMENT
ADVERTISEMENT
Videos
PK Jena
Why Technology Cannot Replace Human Connection in Governance: P.K. Jena
PK Jena
The IAS Officer Who Put People Before Paperwork: How PK Jena Challenged Corruption and Reformed Governance
Keshav kumar
From Police Officer to Forensic Pioneer: How Dr Keshav Kumar Made Science a Weapon Against Crime
ADVERTISEMENT
UPSC Stories
Aayush Sharma
Three CDS Attempts, Five AFCAT Qualifications & Medical Setback: How Aayush Sharma Secured CAPF AIR 135
After three unsuccessful SSB attempts, five AFCAT qualifications and a medical setback, Aayush Sharma...
Tushar Chaudhary IRMS
He Left Intel, Built COPAL-19, Spent Months at AIIMS, Ran Half Marathons, and Returned to UPSC—Tushar Chaudhary’s Journey to IRMS
UPSC ESE AIR 4 Tushar Chaudhary left a ₹25 LPA Intel job, built COPAL-19, spent months at AIIMS, ran...
Mayank Sachan UPSC CAPF
15+ Exam Failures, 15 Years in the Navy: How Mayank Sachan Secured AIR 343 in UPSC CAPF
Former Indian Navy sailor Mayank Sachan secured AIR 343 in UPSC CAPF 2025 after 15+ exam failures, two...
CSR NEWS
Indian Oil Boxing Investment
Indian Oil to Invest Rs 40 Crore Over Two Years to Strengthen India's Boxing Ecosystem and Develop Athletes 
In partnership with NSDF and SAI, Indian Oil will support talent identification, coaching, sports science,...
HURL Project PHULWARI
HURL Signs MoU Under Project PHULWARI to Strengthen Healthcare and Childcare Facilities 
In partnership with Hindustan Latex Family Planning Promotion Trust, HURL will provide need-based medical...
NTPC CCQC
NTPC Bongaigaon Wins Six Gold Awards at CCQC 2026, Adds Two National Honours for Safety and CSR 
The power station earns recognition for quality improvement projects, occupational health and environmental...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Latest
karnataka high court
Karnataka High Court Strikes Down Enhanced SC/ST Quota, Cites 50% Reservation Limit
Telangana High Court
Judicial Dignity in Focus: Telangana High Court Advocates Stage Protest
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Videos
PK Jena
PK Jena
Keshav kumar
ADVERTISEMENT
ADVERTISEMENT