RECPDCL Hands Over Ranipur Chunar Power Transmission SPV to H G Infra Engineering for UP Project

Project Includes Two 220/132/33 kV Substations and a 220 kV Double-Circuit Line; Scheduled for Completion in 18 Months
Indian Masterminds Stories

New Delhi: REC Power Development and Consultancy Limited (RECPDCL), a wholly owned subsidiary of REC Limited under the Ministry of Power, has handed over Ranipur Chunar Power Transmission Limited, a project-specific Special Purpose Vehicle (SPV), to successful bidder H G Infra Engineering Limited for development of an intra-state transmission project in Uttar Pradesh.

The SPV handover took place on September 26, 2026, following the successful completion of the bidding process for the project. H G Infra Engineering emerged as the successful bidder through the Tariff-Based Competitive Bidding (TBCB) process conducted by RECPDCL, which acted as the Bid Process Coordinator.

The project will be developed under the Build, Own, Operate and Transfer (BOOT) model and is aimed at strengthening the intra-state power transmission network in Uttar Pradesh.

Ranipur Chunar Transmission Project: Key Highlights

The project involves the development of new transmission infrastructure across Mau and Mirzapur districts of Uttar Pradesh.

Major components include:

  • 220/132/33 kV Air Insulated Substation (AIS) at Ranipur in Mau
  • 220/132/33 kV AIS at Chunar in Mirzapur
  • A 220 kV double-circuit transmission line from Rasra to Ranipur
  • Associated transmission infrastructure required for the project
  • 18-month implementation schedule

The new infrastructure is expected to strengthen electricity transmission capacity in the relevant areas and support reliable power supply to meet regional requirements.

Read also: RECPDCL Hands Over Sakoli Power Transmission SPV to Ashoka Buildcon for Maharashtra Project

RECPDCL Hands Over SPV to H G Infra Engineering

The formal handover of the project-specific SPV was carried out by Rajesh Raj, Senior General Manager and Head of Department, RECPDCL, to Ujjval Verma, Chief General Manager (Finance), H G Infra Engineering Limited.

Senior officials from RECPDCL, H G Infra Engineering Limited and Uttar Pradesh Power Transmission Corporation Limited (UPPTCL) were also present during the handover ceremony.

The transfer marks the next stage of the project after completion of the competitive bidding process.

Project to Be Developed Under BOOT Model

The Ranipur Chunar Power Transmission Project has been awarded through the Tariff-Based Competitive Bidding mechanism.

Under the arrangement, H G Infra Engineering will develop the project on a Build, Own, Operate and Transfer (BOOT) basis.

The use of competitive bidding and project-specific SPVs is part of the broader approach to developing transmission infrastructure through private-sector participation.

18-Month Timeline for Project Completion

The project has an implementation schedule of 18 months.

Once completed, the two new 220/132/33 kV substations and the associated 220 kV transmission line are expected to strengthen the transmission network in Uttar Pradesh.

The infrastructure will help support reliable transmission of electricity and cater to the power requirements of the relevant regions.

Project at a Glance

  • Project: Ranipur Chunar Power Transmission Project
  • SPV: Ranipur Chunar Power Transmission Limited
  • Successful Bidder: H G Infra Engineering Limited
  • Bid Process: Tariff-Based Competitive Bidding (TBCB)
  • Development Model: Build, Own, Operate and Transfer (BOOT)
  • Substations: Two 220/132/33 kV Air Insulated Substations (AIS)
  • Locations: Ranipur, Mau and Chunar, Mirzapur
  • Transmission Line: 220 kV double-circuit Rasra–Ranipur line
  • Implementation Period: 18 months

Transmission Infrastructure to Strengthen Uttar Pradesh Grid

The Ranipur Chunar project is expected to contribute to the expansion and strengthening of Uttar Pradesh’s intra-state transmission network.

With the construction of two new substations and the Rasra–Ranipur double-circuit transmission line, the project will add new transmission infrastructure in the region.

The handover of the SPV to H G Infra Engineering therefore marks an important step towards the implementation of the project, which is scheduled to be completed within 18 months.

About RECPDCL

REC Power Development and Consultancy Ltd. (RECPDCL) is a wholly owned subsidiary of REC Ltd. It undertakes activities related to power transmission and distribution development, consultancy and project implementation, including facilitating competitive bidding processes for transmission projects.

Read also: RECPDCL, ICAR Sign MoA for 11.1 MW Rooftop Solar Systems Across 76 Institutes in 24 States & UTs


Indian Masterminds Stories
Join our WhatsApp Channel
ADVERTISEMENT
ADVERTISEMENT
Related Stories
ADVERTISEMENT
ADVERTISEMENT
NEWS
Gaganyaan Separation Tests
Why ISRO’s Latest Separation Test is One of the Most Important Test for India’s First Human Spaceflight
Ins samarthak
INS Samarthak Joins Indian Navy: 5 Key Facts About India’s New Warship
Right to Internet Access
Supreme Court Recognises Internet Access As A Fundamental Right For Children
Indian Defence Spending
Indian Defence Spending Push: Why A 35% Modernisation Hike Is Being Sought
IndoWings UCAV_IN_X-2
This Make in India Drone Can Reach and Trace Pakistan Within Minutes 
DRDO STANAG Level 6
DRDO’s New Lightweight Armour Technology Targets 30mm AP Threats
Indian AMCA Programme
These 3 Defence Companies Will Build India's Dream Advanced Medium Combat Aircraft
Defence Minister Rajnath Singh
Defence Minister Rajnath Singh to Represent India at 25th SCO Heads of Government Meeting in Tajikistan on October 19-20
ADVERTISEMENT
ADVERTISEMENT
Videos
Dr Saket Badola IFS
Beyond Tigers and Safaris: How Corbett Literature Festival Wants to Change the Conservation Conversation
PK Jena
Why Technology Cannot Replace Human Connection in Governance: P.K. Jena
PK Jena
The IAS Officer Who Put People Before Paperwork: How PK Jena Challenged Corruption and Reformed Governance
ADVERTISEMENT
UPSC Stories
Bhikan Rojekar UPSC
He missed MBBS by 1 mark in 2016; Maharashtra’s Bhikan Rojekar secures UPSC AIR 812
Bhikan Rojekar secured AIR 812 in UPSC CSE 2025 in his third attempt. Read how the son of a farm labourer...
Umar Janj UPSC CAPF
15+ Failures Couldn’t Stop Him: Umar Janj Secures AIR 160 in UPSC CAPF 2025
After multiple SSB setbacks, a CAPF interview miss by 12 marks and more than 15 failures, Umar Janj secured...
Aayush Sharma
Three CDS Attempts, Five AFCAT Qualifications & Medical Setback: How Aayush Sharma Secured CAPF AIR 135
After three unsuccessful SSB attempts, five AFCAT qualifications and a medical setback, Aayush Sharma...
CSR NEWS
NBCC India CSR Award 2026
NBCC India Wins Award for Excellence in CSR at 4th Fortune Leadership Awards 2026
The recognition honours NBCC’s community welfare initiatives and efforts to improve healthcare accessibility...
HURL ALIMCO
HURL Signs MoU with ALIMCO to Support Divyangjans and Senior Citizens in Gorakhpur, Barauni and Sindri
Under its CSR initiative, HURL will support PMD-VK Gorakhpur and facilitate the distribution of need-based...
MDL CSR Support to Divyasha Vayoshri Kendra
MDL Extends ₹3.79 Crore CSR Support to Divyasha Vayoshri Kendra in Mumbai
The initiative will strengthen access to assistive devices, prosthetics and rehabilitation services for...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Latest
Indian Electoral Rolls SIR ECI Voters
Clean Voter Lists, Also Ensure No Genuine Voter Is Left Out 
Gaganyaan Separation Tests
Why ISRO’s Latest Separation Test is One of the Most Important Test for India’s First Human Spaceflight
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Videos
Dr Saket Badola IFS
PK Jena
PK Jena
ADVERTISEMENT
ADVERTISEMENT