SJVN Faces 10 GW Renewable Energy PPA Delays but Plans 1.5 GW Solar & Major Hydropower Expansion

SJVN CMD Bhupender Gupta cites grid connectivity issues affecting signed agreements; Buxar Thermal Plant nears full commissioning, rooftop solar and Arunachal-Nepal hydropower projects on track
Indian Masterminds Stories

New Delhi: SJVN Limited has revealed that approximately 10 GW of renewable energy (RE) capacity awarded by the company remains without signed Power Purchase Agreements (PPAs) or Power Sale Agreements (PSAs). Speaking during the post-results call for the September quarter, Bhupender Gupta, Chairman and Managing Director (CMD) of SJVN, said the company has floated tenders for 19.8 GW of projects, issued Letters of Award (LOAs) for 13.74 GW, and signed agreements for 3.74 GW so far. Another 3.75 GW is expected to be tied up in the next two months.

Grid Constraints Pose Major Challenge

Gupta highlighted grid connectivity issues as the primary hurdle. “There are transmission line shortages, and because of that, power is not getting evacuated even for commissioned plants,” he said. Connectivity delays—sometimes stretching to 28–31 days—have impacted the company’s ability to meet commissioning targets for several solar projects. SJVN is currently in consultations with the Ministry of Power, Ministry of New and Renewable Energy (MNRE), and project bidders to determine the way forward for projects with issued LOAs but unsigned agreements.

The MNRE recently allowed the potential cancellation of renewable energy project LOAs that show minimal or no progress toward PPAs/PSAs, following case-by-case due diligence.

Read also: SJVN’s Subsidiary Achieves COD for 660 MW Unit at 1320 MW Buxar Thermal Power Plant in Bihar

Upcoming Renewable Energy Additions

SJVN currently operates 13 projects with a total capacity of 3,146 MW. The company plans to commission around 1.5 GW of solar projects by FY27. In the current financial year, SJVN expects to add approximately 650 MW of solar capacity across multiple states, including Rajasthan (Bikaner: 320 MW, Nawa: 100 MW), Bihar (Jamui: 75 MW), Assam (120 MW), and Gujarat (Bagodara: 35 MW).

As a key Renewable Energy Implementing Agency (REIA), SJVN will also float a 1,250 MW battery energy storage tender for Haryana later this year, in addition to a 1,200 MW wind power tender already issued. The company is preparing a tariff-based competitive bidding tender for pumped storage projects as well.

Hydropower Expansion in Arunachal Pradesh and Nepal

SJVN is set to begin construction of the 3,097 MW Etalin Hydroelectric Project in Arunachal Pradesh next year. The project has received forest and environment clearance, and land acquisition is nearing completion, with around 70% of affected people having received compensation. The 688 MW Attunli project in Arunachal Pradesh is expected to move to the construction stage by the end of FY26-27.

Additionally, SJVN plans to start two major hydropower projects in Nepal—the 680 MW Lower Arun and the 900 MW Upper Karnali—in Q1 FY27. Gupta emphasized the strong commercial viability of these projects, noting their attractive tariffs and smooth power sale prospects.

Rooftop Solar under PM-Surya Ghar Scheme

Under the PM-Surya Ghar: Muft Bijli Yojana, SJVN is installing rooftop solar systems on government buildings across Himachal Pradesh, Punjab, and Arunachal Pradesh. Vendor empanelment is complete, and execution is underway for a total of 21.1 MW capacity awarded so far.

Buxar Thermal Plant Nears Full Commissioning

SJVN’s 1,320 MW Buxar Thermal Power Plant is nearing full commissioning. Unit 1 (660 MW) has completed 72-hour full-load testing and is expected to be declared commercially operational within days. The second unit is anticipated to follow by January or February next year. Once fully operational, the plant will generate 9,826 million units annually, with 85% allocated to Bihar and the remainder supplied to the northeastern grid.

Financial Stability and Growth Outlook

Gupta reaffirmed SJVN’s strong financial position, emphasizing the company’s focus on completing under-construction projects to accelerate revenue generation. “We don’t foresee any challenges regarding finances or debt servicing,” he said. “Everything is on track, and we will grow every year with better revenue, better profit, and better capacity addition.”

About SJVN

SJVN Ltd. is a public sector undertaking (PSU) under the Ministry of Power, Government of India. Established in 1988, SJVN is primarily engaged in the development of hydropower, thermal power, and renewable energy projects. The company plays a vital role in strengthening India’s power infrastructure, with a focus on sustainable energy generation. SJVN operates several power plants across India and has a significant portfolio of upcoming projects aimed at increasing the country’s energy capacity.

Read also: SJVN Ltd. Appoints Sipan Kumar Garg as Chief Financial Officer (CFO) to Strengthen Financial Strategy and Governance


Indian Masterminds Stories
Join our WhatsApp Channel
ADVERTISEMENT
ADVERTISEMENT
Related Stories
ADVERTISEMENT
ADVERTISEMENT
NEWS
bihar finance budget
Bihar Sets October 1 Deadline for Departments to Upload Budget Estimates on CFMS
sports bihar
Bihar Builds a New Sports Identity as World-Class Infrastructure Attracts Major Events
punjab case mohanjit singh
Punjab: NCM Seeks DGP Report Over Alleged Assault on Anti-Drug Activist
airport
Bihar Accelerates Airport Projects to Expand Air Connectivity Across the State
sjvn
SJVN Director Rajesh Kumar Chandel Reviews 210 MW Luhri HEP-I and 412 MW Rampur HPS
BPCL Project Pragati
BPCL Project Pragati Achieves 10,000-Mechanic Training Milestone, Boosts BS6 Automotive Skills 
NLC India Renewables Limited (NIRL)
NLC India Renewables Wins 200 MW Wind Power Project Under SJVN’s 600 MW Pan-India Tender
HAL Robotic Drilling Cell
Meet The Technology Behind HAL's Bold Move To Speed Up TEJAS Aircraft Production
ADVERTISEMENT
ADVERTISEMENT
Videos
Keshav kumar
From Police Officer to Forensic Pioneer: How Dr Keshav Kumar Made Science a Weapon Against Crime
ChatGPT Image Aug 20, 2026, 05_46_21 PM
How IPS Officer Keshav Kumar Used Forensics to Crack Gujarat’s Lion Poaching Case
Shakeel Ahmad Ganie IRS Interview
‘My Path Has Not Been Straight’: Shakeel Ahmad Ganie’s Journey to the IRS
ADVERTISEMENT
UPSC Stories
Umar Janj UPSC CAPF AC 2025
After 15 Failures, Umar Janj Finally Heard the Words He Had Been Waiting For: ‘I have made it'
Umar Janj from Jaisalmer secured AIR 160 in UPSC CAPF 2025 after 15+ failures, four attempts, four SSBs...
Abhishek Parmar
NDA Failures, CAPF Setbacks, Then AIR 248:How Abhishek Parmar Overcame Years of Exam Setbacks
Abhishek Parmar became the third generation of his family to enter uniformed service after overcoming...
Naveen Kumar Saini UPSC CAPF
After 3 NDA Attempts and a 7-Mark Miss, Naveen Kumar Saini Gets AIR 7 in UPSC CAPF 2025
Naveen Kumar Saini secured AIR 7 in UPSC CAPF 2025 after multiple NDA and SSB failures and missing CAPF...
CSR NEWS
BPCL Project Pragati
BPCL Project Pragati Achieves 10,000-Mechanic Training Milestone, Boosts BS6 Automotive Skills 
CSR initiative with ASDC provides mechanics training in BS6 engines, advanced diagnostics, vehicle electrical...
BEL CSR Tipper Vehicles
BEL Donates 10 Tipper Vehicles to UPSIDA for Industrial Garbage Collection in Ghaziabad
CSR initiative will support door-to-door industrial waste collection across five industrial areas, strengthening...
BPCL Varanasi
BPCL Signs Two MoUs Worth ₹69.21 Crore to Transform Varanasi’s Parks, Heritage and Tourism Infrastructure 
The CSR initiatives will modernise 119 public parks, create food street hubs at Sarnath and Maidagin,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Latest
bihar finance budget
Bihar Sets October 1 Deadline for Departments to Upload Budget Estimates on CFMS
sports bihar
Bihar Builds a New Sports Identity as World-Class Infrastructure Attracts Major Events
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Videos
Keshav kumar
ChatGPT Image Aug 20, 2026, 05_46_21 PM
Shakeel Ahmad Ganie IRS Interview
ADVERTISEMENT
ADVERTISEMENT