NTPC Restores 2,100 MW Generation at Korba Plant; 500 MW Unit-6 to Return by Month-End 

Six of seven units at the 2,600 MW Chhattisgarh plant are back on the grid, while 500 MW Unit-6 remains under planned overhaul and is expected to return by month-end. 
Indian Masterminds Stories

New Delhi: NTPC Limited has restored power generation from six of the seven units at its 2,600 MW Korba power station in Chhattisgarh, around two days after an electrical fault caused all operating units at the coal-based plant to trip on September 4.

The six restored units account for 2,100 MW of the station’s installed capacity. The remaining 500 MW Unit-6 has been under a planned biennial overhaul since August 25 and is expected to return to the grid by the end of September.

Six Units Restored After Sequential Restart

The restoration was carried out in phases in accordance with established safety and operational procedures, as the units could not be restarted simultaneously following the total shutdown.

The restoration sequence was:

  • Unit-4 (500 MW): Restored within 12 hours
  • Unit-5 (500 MW): Restored within 12 hours
  • Unit-1 (200 MW): Restored within 12 hours
  • Unit-3 (200 MW): Restored within 36 hours
  • Unit-2 (200 MW): Restored on September 6 at 8:40 pm
  • Unit-7 (500 MW): Restored on September 6 at 9:20 pm

With these six units back online, 2,100 MW of generation capacity has been restored at the Korba station.

Read also: NTPC Wins ‘Most Consistent Performer’ Award at XLRI’s HR for the Greater Good Conclave 2026

Electrical Fault Caused Simultaneous Tripping

The outage occurred shortly after 6 pm on September 4, when the units at the coal-based power station in Korba city’s Darri area tripped simultaneously.

According to NTPC, the incident was caused by an electrical fault during testing of a breaker at a Power Grid Corporation of India Limited (PGCIL) bay.

The simultaneous tripping resulted in what an NTPC official described as a “blackout-like situation” inside the generating station.

NTPC subsequently initiated the restoration process in phases, with the cause of the electrical fault being investigated.

Unit-6 Remains Under Planned Overhaul

While six units have resumed generation, 500 MW Unit-6 remains unavailable as it is undergoing a scheduled biennial planned overhaul.

The unit was taken under shutdown on August 25, before the September 4 electrical fault occurred.

NTPC said Unit-6 is expected to be brought back to the grid by the end of September. Until then, 500 MW of the station’s total capacity will remain unavailable on a planned basis.

Korba Power Station Has 2,600 MW Capacity

The NTPC Korba power station consists of seven generating units with a combined installed capacity of approximately 2,600 MW.

The station comprises:

  • Four units of 500 MW each
  • Three units of 200 MW each

The coal-based power station supplies electricity to several beneficiary states through the interconnected power grid, making its generation availability important for regional power supply.

NTPC Focuses on Safe Restoration

NTPC said the remaining units were restored sequentially in line with established safety and operational procedures following the total shutdown.

The phased restoration allowed the generating units to be brought back online safely while the company continued to assess the circumstances surrounding the September 4 electrical fault.

With six units now operational, the station has regained most of its generation capacity, while the final 500 MW unit is scheduled to return after completion of its planned overhaul.

About NTPC

NTPC Limited is India’s largest power utility and a central public sector enterprise under the Ministry of Power. The company is engaged in electricity generation and has a diversified portfolio spanning thermal, renewable and other energy-related projects, supporting India’s power security and energy transition.

Read also: NTPC REL Energy Secures 500 MW SECI Contract at ₹6/kWh for Assured Peak Renewable Power


Indian Masterminds Stories
Join our WhatsApp Channel
ADVERTISEMENT
ADVERTISEMENT
Related Stories
ADVERTISEMENT
ADVERTISEMENT
NEWS
Gaganyaan Separation Tests
Why ISRO’s Latest Separation Test is One of the Most Important Test for India’s First Human Spaceflight
Ins samarthak
INS Samarthak Joins Indian Navy: 5 Key Facts About India’s New Warship
Right to Internet Access
Supreme Court Recognises Internet Access As A Fundamental Right For Children
Indian Defence Spending
Indian Defence Spending Push: Why A 35% Modernisation Hike Is Being Sought
IndoWings UCAV_IN_X-2
This Make in India Drone Can Reach and Trace Pakistan Within Minutes 
DRDO STANAG Level 6
DRDO’s New Lightweight Armour Technology Targets 30mm AP Threats
Indian AMCA Programme
These 3 Defence Companies Will Build India's Dream Advanced Medium Combat Aircraft
Defence Minister Rajnath Singh
Defence Minister Rajnath Singh to Represent India at 25th SCO Heads of Government Meeting in Tajikistan on October 19-20
ADVERTISEMENT
ADVERTISEMENT
Videos
Dr Saket Badola IFS
Beyond Tigers and Safaris: How Corbett Literature Festival Wants to Change the Conservation Conversation
PK Jena
Why Technology Cannot Replace Human Connection in Governance: P.K. Jena
PK Jena
The IAS Officer Who Put People Before Paperwork: How PK Jena Challenged Corruption and Reformed Governance
ADVERTISEMENT
UPSC Stories
Bhikan Rojekar UPSC
He missed MBBS by 1 mark in 2016; Maharashtra’s Bhikan Rojekar secures UPSC AIR 812
Bhikan Rojekar secured AIR 812 in UPSC CSE 2025 in his third attempt. Read how the son of a farm labourer...
Umar Janj UPSC CAPF
15+ Failures Couldn’t Stop Him: Umar Janj Secures AIR 160 in UPSC CAPF 2025
After multiple SSB setbacks, a CAPF interview miss by 12 marks and more than 15 failures, Umar Janj secured...
Aayush Sharma
Three CDS Attempts, Five AFCAT Qualifications & Medical Setback: How Aayush Sharma Secured CAPF AIR 135
After three unsuccessful SSB attempts, five AFCAT qualifications and a medical setback, Aayush Sharma...
CSR NEWS
NBCC India CSR Award 2026
NBCC India Wins Award for Excellence in CSR at 4th Fortune Leadership Awards 2026
The recognition honours NBCC’s community welfare initiatives and efforts to improve healthcare accessibility...
HURL ALIMCO
HURL Signs MoU with ALIMCO to Support Divyangjans and Senior Citizens in Gorakhpur, Barauni and Sindri
Under its CSR initiative, HURL will support PMD-VK Gorakhpur and facilitate the distribution of need-based...
MDL CSR Support to Divyasha Vayoshri Kendra
MDL Extends ₹3.79 Crore CSR Support to Divyasha Vayoshri Kendra in Mumbai
The initiative will strengthen access to assistive devices, prosthetics and rehabilitation services for...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Latest
Indian Electoral Rolls SIR ECI Voters
Clean Voter Lists, Also Ensure No Genuine Voter Is Left Out 
Gaganyaan Separation Tests
Why ISRO’s Latest Separation Test is One of the Most Important Test for India’s First Human Spaceflight
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
Videos
Dr Saket Badola IFS
PK Jena
PK Jena
ADVERTISEMENT
ADVERTISEMENT